Tender invited for Survey work for Delhi-Amritsar High Speed Rail Project

Anushka Khare Posted on: 2020-09-20 12:36:00 Viewer: 2,926 Comments: 0 Country: India City: New Delhi

Tender invited for Survey work for Delhi-Amritsar High Speed Rail Project

New Delhi, India (Urban Transport News): The National High Speed Rail Corporation Limited (NHSRCL) on 19th October 2020 issued the first tender notice for preparatory survey work to prepare the Detailed Project Report (DPR) for the proposed 459 km Delhi - Chandigarh - Amritsar High Speed Rail project.

Scope of work

The survey, Identification of Overhead, Over Ground, Underground Utilities And Identification Of Power Sourcing Options for substations along the proposed Delhi – Chandigarh – Amritsar High Speed Rail Corridor.

Key Information

  • Tender Notice No.: NHSRCL/ST/DAM/04/DLI-CHD -AMR HSRTend./79/.2
  • Issue Date: 19th October 2020
  • Estimated Tender Value: NA
  • Security Money Deposit: Rs 1,69,900.00
  • Work Completion Period: 14 Weeks
  • Dates of submission of Bids: 03.11.2020 (from 09:00 hrs) to 09.11.2020 (up to 15:00 hrs)
  • Opening Date of Technical Bids: 10.11.2020 at 15:30 hrs.

Pre-bid Meeting and Contact Point

A pre-bid meeting is scheduled on 28.10.2020 at 11.00 hrs through video conferencing. Interested bidders may contact Executive Director/Electrical, National High Speed Rail Corporation Ltd., 2nd Floor, Asia Bhawan, Road No. 205, Sector-9, Dwarka, New Delhi-110077 for further details.

Project details

The proposed 459 km long Delhi – Chandigarh – Amritsar High Speed Rail Corridor will connect Delhi to Amritsar through 6 intermediate stations that are tentatively planned to be built at Delhi, Sonipat, Panipat, Ambala, Chandigarh, Ludhiana, Jalandhar and Amritsar. This corridor the fourth high-speed rail project proposed by the Government of India.

A consortium of RITES Limited and Systra MVA had completed the feasibility report of this project. According to the feasibility report of this submitted to the Ministry of Railways in 2017, the cost of the project was estimated to Rs 61,412 crore at a 2015 price level.

For more details, please explore the Delhi -  Amritsar High Speed Rail page of Urban Transport News.





Also Read




Leave Your Comment!









Recent Comments!

No comments found...!