Mumbai Metro: Project Information, Tenders, Stations, Routes and Updates

Anushka Khare Posted on: 2020-09-10 22:19:00 Viewer: 26,094 Comments: 0 Country: India City: Mumbai

Mumbai Metro: Project Information, Tenders, Stations, Routes and Updates

Mumbai Metro Rail Project consists of a total of 14 metro lines, will connect the entire Mumbai City through the metro rail network to help in reducing human traffic.

  • Project Name: Mumbai Metro Rail Project
  • Nodal Body: Mumbai Metropolitan Region Development Authority (MMRDA)
  • Owner: Govt. of India and Govt. of Maharashtra
  • Project Type: Mass Rapid Transit System (MRTS)
  • Total Network Planned: 337.1 km
  • Estimated Project Cost: ₹1,40,814 Crore
  • Operation Network: 11.4 km
  • Operational Since: 8th June 2014

Nodal Body

  • Mumbai Metropolitan Region Development Authority (MMRDA): Line 1, 2, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14
  • Mumbai Metro Rail Corporation Ltd. (MMRC): Line 3 (Underground)

Key Figures

Line

Corridor

Length

Stations

Construction Start Date

Completion Target

1

Versova-Ghatkopar

11.4 km

12

February 8, 2008

Operational

2A

Dahisar-DN Nagar

18.6 km

16

July 2016

January 2023

2B

DN Nagar-Mandale

23.6 km

22

January 2018

June 2024

3

Colaba-SEEPZ

33.5 km

27

July 2016

Feb. 2022-23

4

Wadala-Kasarwadavali

32.3 km

32

April 2018

Feb. 2024

4A

Kasarwadavali-Gaimukh

2.7 km

2

September 2019

Feb. 2024

5

Thane-Bhiwandi-Kalyan

24.9 km

17

September 2019

Oct 2024

6

Samarthnagar-Vikhroli

14.5 km

13

October 2018

Feb 2024

7

Dahisar (E)-Andheri (E)

16.5 km

13

June 2016

January 2023

7A

Andheri (E)-CSIA

2.12 km

2

September 2019

October 2024

8

CSIA-NMIA

35 km

TBD

TBD

October 2026

9

Dahisar (E)-Mira Bhayandar

11.38 km

9

September 2019

October 2024

10

Gaimukh-Shivaji Chowk

9.2 km

4

August 2020

October 2024

11

Wadala-CSMT

12.7 km

10

August 2020

October 2026

12

Kalyan-Taloja

20.7 km

17

August 2020

October 2024

13

Shivaji Chowk-Virar

23 km

TBD

TBD

October 2026

14

Kanjurmarg-Badalapur

45 km

TBD

TBD

October 2026

[Source: Extracts from the latest interaction with Mr. RA Rajeev, Metropolitan Commissioner, MMRDA]

Operational Network

Blue Line 1: Varsova - Ghatkopar

  • Length: 11.4 km
  • No. of Stations: 12 (elevated)
  • Project Cost: ₹2,356 crores
  • Start date of operation: 8 June 2014
  • Operator: Mumbai Metro One Pvt. Ltd. (A JV of Reliance Infra and RATP Dev-Transdev Asia)
  • Station Names: Versova, D.N. Nagar, Azad Nagar, Andheri, Western Express Highway, Chakala, Airport Road, Marol Naka, Saki Naka, Asalpha, Jagruti Nagar, Ghatkopar
  • Depot: DN Nagar

Yellow Line 2A: Dahisar East - DN Nagar

  • Length: 18.5 km (10 km operational)
  • No. of Stations: 16 (elevated)
  • Project Cost: ₹6,410 crores
  • Deadline: May 2021
  • Operational: Dahisar East, Upper Dahisar, Kandarpada, Mandapeshwar, Eksar, Borivali (West), Pahadi Eksar, Kandivali (West), Dahanukarwadi, Valnai, Malad (West), Lower Malad, Pahadi Goregaon, Goregaon (West), Oshiwara, Lower Oshiwara and Andheri (West).

Red Line 7: Andheri (East) - Dahisar (East)

  • Length: 16.475 km (10 km)
  • No. of Stations: 13 (elevated)
  • Project Cost: ₹6,208 crores
  • Deadline: May 2021
  • Operational: Dahisar (East), Ovaripada, National Park, Devipada, Magathane, Mahindra & Mahindra, Bandongri, Pushpa Park, Pathan Wadi, Aarey, Mahanand, JVLR Junction, Shankarwadi, and Andheri (East).

Under Construction Projects

Yellow Line 2B: DN Nagar - Mandale

  • Length: 23.643 km
  • No. of Stations: 22 (elevated)
  • Project Cost: ₹10,986 crores
  • Deadline: 2022
  • Station Names: ESIC Nagar, Prem Nagar, Indira Nagar Nanavati Hospital, Khira Nagar, Saraswat Nagar, National College, Bandra Metro, MMRDA, ITO-BKC, IL&FS-BKC, MTNL-BKC, SG Barve Marg, Kurla Terminus, Kurla (East), Eastern Express Highway, Chembur, Diamond Garden, Shivaji Chowk, BSNL, Mankhurd and Mandale.

Aqua Line 3: Cuffe Parade - Aarey Depot (Colaba–Bandra-SEEPZ)

  • Length: 33.5 km
  • No. of Stations: 27 (26 underground, 1 at-grade)
  • Project Cost: ₹23,136 crores
  • Deadline: 2021
  • Station Names: Cuffe Parade, Vidhan Bhavan, Churchgate, Hutatma Chowk, CST, Kalbadevi, Girgaon, Grant Road, Mumbai Central, Mahalaxmi, Science Museum, Acharya Atrey Chowk, Worli, Siddhivinayak, Dadar, Shitladevi Temple, Dharavi, BKC, Vidyanagri, Santacruz, CSIA Domestic, Sahar Road, CSIA International, Marol, MIDC, SEEPZ and Aarey.

Green Line 4: Wadala - Kasarvadavali

  • Length: 32.32 km
  • No. of Stations: 32 (elevated)
  • Project Cost: ₹14,549 crores
  • Deadline: 2022
  • Station Names: Bhakti Park Metro, Wadala TT, Anik Nagar Bus Depot, Suman Nagar, Siddharth Colony, Amar Mahal Junction, Garodia Nagar, Pant Nagar, Laxmi Nagar, Shreyas Cinema, Godrej Company, Vikhroli Metro, Surya Nagar, Gandhi Nagar, Naval Housing, Bhandup Mahapalika, Bhandup Metro, Shangrila, Sonapur, Mulund Fire Station, Mulund Naka, Thane Teen Haath Naka, RTO Thane, Mahapalika Marg, Cadbury Junction, Majiwada, Kapurbawdi, Manpada, Tikuji-Ki-Wadi, Dongari Pada, Vijay Garden, Kasarvadavali

Green Line 4A: Kasarvadivli - Gaimukh

  • Length: 2.7 km
  • No. of Stations: 2 (elevated)
  • Project Cost: ₹949 crores
  • Deadline: 2022
  • Station Names: Gowanipada, Gaimukh

Orange Line 5: Thane - Kalyan

  • Length: 24.9 km
  • No. of Stations: 17 (elevated)
  • Project Cost: ₹8,417 crores
  • Deadline: 2024
  • Station Names: Kapurbawdi, Balkum Naka, Kasheli, Kalher, Purna, Anjur Phata, Dhamankar Naka, Bhiwandi, Gopal Nagar, Temghar, Rajnouli Village, Goregaon MIDC, Kongaon, Durgadi Fort, Sahajanand Chowk, Kalyan Railway Station, Kalyan APMC.

Pink Line 6: Lokhandwala-Jogeshwari-Vikhroli-Kanjurmarg

  • Length: 14.47 km
  • No. of Stations: 13 (elevated)
  • Project Cost: ₹6,716 crores
  • Deadline: 2022
  • Station Names: Swami Samarth Nagar, Adarsh Nagar, Jogeshwari West, Jogeshwari-Vikhroli Link Road, Shyam Nagar, Mahakali Caves, SEEPZ Village, Saki Vihar Road, Ram Baug, Powai Lake, IIT Powai, Kanjurmarg West, and Vikhroli-Eastern Express Highway.

Red Line 7A: Andheri (East) - CSIA

  • Length: 2.15 km
  • No. of Stations: 2 (1 elevated, 1 underground)
  • Project Cost: ₹600 crores
  • Deadline: October 2024

Gold Line 8: CSIA - NMIA

  • Length: 35 km
  • Project Cost: ₹15,000 crores
  • Deadline: October 2026

Red Line 9: Dahisar East - Bhayandar

  • Length: 10.41 km
  • No. of Stations: 9 (elevated)
  • Project Cost: ₹6,007 crores
  • Deadline: October 2024
  • Station Names: Pandurang Wadi, Amar Palace, Zankar Company, Sai Baba Nagar, Deepak Hospital, Shahid Bhagat Singh Garden, Subhash Chandra Bose Stadium, MBMC Sports complex, Indiralok

Green Line 10: Gaimukh - Shivaji Chowk (Mira Road)

  • Length: 9.209 km
  • No. of Stations: 4 (elevated)
  • Project Cost: ₹4,476 crores
  • Deadline: October 2024

Green Line 11: Wadala to Chhatrapati Shivaji Maharaj Terminus

  • Length: 12.774 km
  • No. of Stations: 10 (2 elevated, 8 underground)
  • Project Cost: ₹8,739 crores
  • Deadline: October 2026

Orange Line 12: Kalyan - Taloja

  • Length: 20.756 km
  • No. of Stations: 17 (elevated)
  • Project Cost: ₹ 5,865 crores
  • Deadline: October 2024

Purple Line 13: Shivaji Chowk - Virar

  • Length: 23 km (Elevated)
  • Project Cost: ₹6,900 crores
  • Deadline: October 2026

Magenta Line 14: Kanjurmarg - Badlapur

  • Length: 45 km (Elevated)
  • Project Cost: ₹13,500 crores
  • Deadline: October 2026

Metro Authority Contact details

Mumbai Metropolitan Region Development Authority

BANDRA-KURLA COMPLEX,

C-14 & 15, E BLOCK BANDRA

(EAST)400 051

Tel: 22-26594000

Email: NA

Website: mmrda.maharashtra.gov.in